Parameters, Timelines, and Costs
Knowing how to turn or mill isn’t enough: in the shop, you also need to know how long it takes to make a workpiece and how much it costs. In this chapter, we’ll outline the machining operations in a cycle, select the parameters using a systematic method, calculate the cycle time and the hourly machine cost, determine the cost of the workpiece and prepare a quote, and conclude by addressing the most common machining issues and ways to shorten cycle time.
30.1 The Machining Cycle
The machining cycle is the ordered list of all the steps involved in transforming the blank (a bar, a casting, a blank) into the finished part specified in the technical drawing. It is prepared by the engineering department or the production engineer before the batch enters the shop floor. The cycle is divided into three levels:
- phase: everything that's done on the workpiece in the same machine or workstation (the saw, the lathe, the milling machine, the inspection station). The steps are numbered in increments of ten (10, 20, 30...), so a new step can be added without having to renumber everything;
- sub-phase: the part of a phase consisting of a single placement, that is, without removing and re-mounting the workpiece. If the workpiece is rotated in the jaws halfway through a phase, a new sub-phase begins (20.1, 20.2...);
- operation: a basic machining process performed with a single tool and the same parameters: facing, roughing, drilling (20.1.1, 20.1.2...).
The order of the steps is not random. The most common rules are: first, work on the surfaces that serve as reference As for the others, first... rough cut everything, and then yes ends (if heat treatment is involved, it comes in the middle: Chapter 22); dimensions subject to tight tolerances are produced in the same ranking, because every time you take the workpiece apart, you lose a little precision; you're looking for the fewer placements possible, because every placement takes time.
Production Schedule and Work Order for Machining Operations
The production cycle is documented in two documents. The production cycle sheet describes how the workpiece is made: for each phase and operation, it specifies the machine, the clamping equipment, the tool, the cutting parameters, and the estimated time, often accompanied by a small drawing of the phase. This is the technical document, which is the same for all batches of the same workpiece. Here is the process sheet for the C45 pin from Example 26.14 (bar Ø80, pin Ø62, 120 mm long, Ra 1.6 µm):
| Phase | Operation | Machine and Outlet | Tool | Vc (m/min) | n (rpm) | f (mm/revolution) | ap (mm) | Time(s) |
|---|---|---|---|---|---|---|---|---|
| 10 | Cutting a section Ø80 × 166 | Band saw, vise | Bimetal blade | 72 | ||||
| 20.1.1 | Facing (1 mm) | CNC lathe, chuck, 45 mm | T0101 rhombic 80°, rε 1.2 | 180 (G96) | 716-4000 | 0,2 | 1 | 8,7 |
| 20.1.2 | Roughing: Ø80 → Ø62.6 in 3 passes | as above | T0101 | 200 | 858-1017 | 0,3 | 2,9 | 78,6 |
| 20.1.3 | Finishing Ø62 | as above | T0303 rhombic 55°, rε 0.8 | 250 | 1284 | 0,1 | 0,3 | 57,0 |
| 30 | Deburring, Ø62 and Ra inspection | Test Bench | 50-75 Micrometer, Roughness Tester | on a sample basis |
The machining order (or phase sheet), on the other hand, is the document that accompanies the batch in the workshop. It specifies which batch it is, how many workpieces there are, which phase is being carried out, and records what actually happens: who worked on it, how long it took, how many good workpieces, and how many rejects. It is used for traceability (if a workpiece breaks at the customer’s site, it is possible to trace it back to the batch, the machine, and the operator) and for performance analysis—that is, comparing planned times with actual times. Here is an example filled out for stage 20 of the pin:
| Production Order | OP 2026/0418 | Code and Drawing | PRN-062 Rev. B |
| Description | Pin Ø62 × 120 | Material | Drawn C45, Ø80 |
| Lot Quantity | 200 workpieces | Phase | 20 · CNC turning |
| Machine | CNC Lathe No. 3 | Program | O2062 |
| Planned Equipment | 45 min | Estimated time per workpiece | 221.4 s (Example 30.5) |
| Date | Operator | Setup (h) | Hours worked | Good Workpieces | Waste | Notes |
|---|---|---|---|---|---|---|
| 16/11 | G. R. | 0,8 | 6,5 | 97 | 2 | 2 workpieces, Ø62, below tolerances on first startup |
| 17/11 | G. R. | 0 | 6,4 | 101 | 0 | closed lot |
| Total | 0,8 | 12,9 | 198 | 2 | Check: Phase 30 | |
The worksheet immediately shows that the actual setup time (0.8 h, or 48 minutes) was slightly longer than expected and that two good workpieces are missing: the supervisor decides whether to rework them or ship 198 as agreed with the customer.
30.2 Selecting Parameters Step by Step
Cutting parameters aren't chosen at random, and they aren't all chosen at once. You follow a specific order, because each choice limits the next one:
- Material and ISO group: Identify the material from the drawing and place it in its corresponding group (P for steels, M for stainless steels, K for cast iron, N for non-ferrous metals, S for superalloys and titanium, H for hardened steels: Chapters 24 and 25);
- Tool: insert shape and size, nose radius, chipbreaker, and grade suitable for the assembly and the machining operations;
- pass depth ap: the largest size that the workpiece, the insert, and the machine can handle, so fewer passes are needed;
- feed rate f: the highest rate compatible with the chipbreaker, the strength of the cutting edge, and, for finishing operations, the required roughness;
- cutting speed Vc: finally, refer to the supplier’s table, because it determines the life of the cutting edge (Taylor’s Law and the minimum-cost speed are discussed in Chapter 24);
- Checks: Calculate revolutions, feed rate, force, and power (Chapter 26), as well as the theoretical roughness; if something doesn't add up, go back and correct it.
A quenched and tempered 42CrMo4 steel shaft is to be turned from Ø70 to Ø60 over a length of 150 mm, with a surface roughness of Ra 3.2 µm. The lathe has a 7.5 kW motor with an efficiency of 0.8. An 80° rhombic insert with rε = 0.8 mm and κr = 95° is used, cutting to a depth of up to 4 mm; for this material, kc1 = 2000 N/mm² and mc = 0.25.
30.3 Initial Parameters for Turning, Milling, and Drilling
The table compiles the starting values for the three most common machining operations, by ISO group, in a single location. For turning, these are the roughing values from Table 26.12 (which also includes finishing values); for milling, the values refer to coated carbide-tipped end mills for face milling and contouring (Chapter 27), with the feed per tooth (fz); for drilling, solid carbide drills with diameters ranging from 8 to 12 mm (Chapter 28).
| ISO Group and Material | Turning (roughing) | Milling | Drilling | |||
|---|---|---|---|---|---|---|
| Vc (m/min) | f (mm/revolution) | Vc (m/min) | fz (mm/tooth) | Vc (m/min) | f (mm/revolution) | |
| P · non-alloy steel (C40, C45) | 180-250 | 0,25-0,5 | 180-280 | 0,1-0,25 | 80-120 | 0,15-0,3 |
| P · quenched and tempered alloy steel | 140-200 | 0,2-0,4 | 150-220 | 0,1-0,2 | 70-100 | 0,12-0,25 |
| M · austenitic stainless steel | 120-180 | 0,15-0,35 | 120-180 | 0,08-0,15 | 40-70 | 0,08-0,18 |
| K · gray cast iron | 160-250 | 0,2-0,5 | 150-250 | 0,1-0,25 | 80-130 | 0,2-0,35 |
| N · aluminum alloys | 300-800 | 0,2-0,5 | 400-1200 | 0,08-0,2 | 150-300 | 0,2-0,4 |
| N · brass | 200-400 | 0,15-0,4 | 200-400 | 0,08-0,2 | 100-200 | 0,15-0,3 |
| S · titanium (Ti6Al4V) | 40-70 | 0,1-0,3 | 40-70 | 0,05-0,12 | 25-45 | 0,08-0,15 |
| S · nickel superalloys | 25-50 | 0,1-0,25 | 25-45 | 0,05-0,1 | 15-30 | 0,05-0,12 |
| H · Hardened steel, 55–60 HRC | 80–150 (CBN) | 0,05-0,2 | 80-150 | 0,05-0,1 | 30-60 | 0,05-0,12 |
A guideline table prepared by CNC Simulator Italia, with rounded average values, for training purposes and for the first workpiece. The correct values for a specific tool are provided by its supplier. With high-speed steel (HSS) tools, cutting speeds drop to about one-third for drilling and to one-fifth or less for turning and milling.
30.4 Machining Times
The time that passes between one workpiece and the next is made up of different workpieces, and it’s best to call them by their proper names:
- cutting time (or active time): the tool is in the material and is removing chips. It is calculated using the formulas in Chapters 26, 27, and 28;
- Passive times: the machine moves but does not cut. These include rapid movements (G00) to approach and retract, returns to the start of the pass, tool changes, spindle start and stop, and range changes;
- machine time: the sum of the two, that is, the time the program runs;
- Manual operations: tasks performed by the operator, such as loading and unloading the workpiece, cleaning the jaws, and taking measurements. If these are performed while the machine is stopped, they are added to the machine time; if they are performed while the machine is running (for example, measuring the previous workpiece), they are referred to as shadow time and do not extend the cycle time;
- cycle time: the time between the release of one workpiece and the release of the next.
A 300-mm-long C45 plate is machined flat using a 5-tooth Ø63 insert-tipped end mill, with Vc = 200 m/min and fz = 0.15 mm/tooth. The end mill passes through the center of the workpiece and must exit completely; add 3 mm of approach and 3 mm of exit (the calculation of the milling travel is explained in Chapter 27).
On a machining center, 8 holes with a diameter of 10 and a depth of 20 mm are drilled into a C45 plate. First, the workpiece is centered using a center drill (1,500 rpm, f = 0.1 mm/rev, travel 3 + 2 = 5 mm), then holes are drilled using a carbide drill bit (Vc = 90 m/min, f = 0.2 mm/rev). The drilling travel is 20 mm plus the tapered drill (approximately 0.3 × D = 3 mm) plus 2 mm of approach. Each movement from one hole to the next, including rapid ascent and descent, takes 1.0 s; each tool change, from chip to chip, takes 5 s.
For workpieces that require many small machining operations, non-cutting times can account for nearly as much of the total time as the cutting time itself: to shorten the cycle time, it is more effective to reduce movements and tool changes than to increase the cutting speed.
In Example 26.14, the pin has a cutting time of 144.3 s (facing 8.65 s, roughing 78.6 s, finishing 57.0 s). Now let’s add the rest, using these shop floor data (fictitious but realistic): throughout the program, the turret travels 1,500 mm in rapid traverse at an average speed of 10 m/min, including acceleration and deceleration; there are 2 tool changes (T0101 → T0303 and back) taking 3 s each; the spindle starts and stops once, taking 2 s per operation; Manual loading and unloading of the workpiece, with the machine stopped, takes 30 s; one out of every five workpieces is measured on the machine with a micrometer, taking 40 s.
30.5 Setup, surcharges, and time per workpiece
Before machining the first workpiece of a batch, the machine must be set up: the correct jaws are installed, the tools and program are loaded, the offsets are measured, the origin is set, the first workpiece is machined, and it is inspected. This time, tatt, is spent once per batch and must be divided among the N workpieces in the batch.
Then there's the fact that no one works eight hours straight at the same pace. The measured or calculated time is increased by applying percentage-based adjustments:
- the rest factor (or from fatigue): recovery after heavy, repetitive work or work in a hot and noisy environment;
- the physiological factor: personal needs (drinking, using the restroom), which cannot be eliminated;
- often a small dimension set aside for unexpected expenses (a chip to remove, an extra check).
In machine shops, the total is usually between 5 and 15 percent. Here, the surcharge applies to the entire cycle time, because on a lathe without a feeder, when the operator stops, the machine stops as well.
The pin in Example 30.4 (cycle time = 201.3 s) is produced in a batch of 200 workpieces. Setup takes 45 minutes, and the markup is 10%. What is the time per workpiece, and how many workpieces are produced in an 8-hour shift?
30.6 Plant Performance (OEE)
A machine may appear fast on paper but actually produce very little in reality—because it is idle due to breakdowns and setup times, because it operates more slowly than expected, or because it produces scrap. OEE (Overall Equipment Effectiveness) combines these three types of losses into a single figure:
- Availability D: the portion of scheduled time during which the machine actually operated (excluding breakdowns, setup times, and waiting for materials);
- Efficiency E (or performance): the amount produced compared to what would have been produced in the expected cycle time (slowsdowns, micro-stops, and reduced feeds set with the selector are not accounted for);
- Quality Q: the proportion of produced workpieces that are good (excluding scrap and workpieces requiring rework).
An 8-hour shift with a scheduled 30-minute break. During the shift: 45 minutes of setup, a 20-minute breakdown of the coolant system. A total of 100 pins were produced (cycle time = 201.3 s), of which 3 were rejected.
Verification: 97 good workpieces · 201.3 s = 325.4 min, and 325.4 / 450 = 0.723. In theory, with an OEE of 1, 450 · 60 / 201.3 = 134 good pins would have been produced in 450 minutes.
As a general rule of thumb, many workshops fall between 50 and 65 percent; 85 percent is considered an excellent result. Knowing the three separate figures is more useful than the final number: it indicates where to take action (fewer breakdowns, faster setup times, fewer micro-stops, less scrap).
30.7 The hourly cost of machinery and labor
To find out how much a workpiece costs, you need to know how much an hour of machine time costs. The hourly cost of the machine takes all the expenses the machine incurs in a year and divides them by the number of hours it operates:
- depreciation: the loss in value of the machine, spread over its useful life;
- interest: the cost of the money invested in the machine (if borrowed, the interest paid to the bank; if it is the owner’s own money, the return it would have earned elsewhere), calculated on the average capital tied up;
- space: the dimension of the rent, heating, and lighting costs for the warehouse based on the square meters occupied (machine plus work area);
- energy: electricity consumption, with the average power draw much lower than the installed capacity;
- maintenance: routine and major, usually estimated as a percentage of the price;
- General tools and consumables: tool holders, jaws, coolant, oil, filters. The inserts, which depend on the workpiece, are counted separately (section 30.8).
Fictitious but realistic data for a medium-sized CNC lathe in 2026: installed price €150,000, useful life 10 years, residual value €15,000; interest rate of 4%; occupies 30 m² at €90/m² per year; maintenance costs 3% of the price per year; average power consumption 7 kW (installed capacity 22 kW), electricity at 0.25 €/kWh; general tooling and consumables 2,600 € per year; one shift, 1,600 hours of actual work per year.
Labor costs are calculated in the same way: the company’s annual cost for the employee (gross salary plus social security contributions, severance pay, and insurance) divided by the actual hours worked, which are fewer than the hours paid due to vacation, holidays, time off, and sick leave.
The operator costs the company €37,800 per year (approximately €27,600 gross plus €10,200 in social security contributions, severance pay, and insurance) and works 1,680 actual hours. Calculate the hourly cost of the operator and that of the lathe plus the operator; then recalculate the cost if the same operator operates two identical lathes.
In the following examples, Ch is set to 40.875 €/h, which is 40.875 / 3600 = 0.01135 € per second.
30.8 Tooling Cost per Workpiece
A cutting edge lasts for a certain cutting time T (its service life, which depends primarily on the cutting speed: Taylor’s law, Chapter 24), after which it must be turned or replaced. The cost of a cutting edge includes its price (the price of the insert divided by the number of usable cutting edges), a portion of the tool holder’s cost—which lasts for a few hundred cutting edges—and the cost of the time the machine is idle during replacement. This cost is spread across the workpieces that the cutting edge is able to produce.
Roughing and facing with T0101: 12 € insert with 4 cutting edges, tool holder dimension 0.40 € per cutting edge, tool life T = 15 min, cutting time per workpiece 8.65 + 78.6 = 87.25 s. Finishing with T0303: €14 insert with 4 cutting edges, same tool holder dimension, T = 20 min, cutting time 57.0 s. Replacing a cutting edge stops the machine for 2 minutes; Ch = €40.875/h.
Increasing the cutting speed reduces cutting time, but the tool life (T) decreases much more: beyond a certain point, the cost of the inserts increases more than the time saved. The “minimum-cost speed” discussed in Chapter 24 indicates where the balance lies.
30.9 The cost per workpiece
Now all the workpieces on the bill are listed. The cost of a workpiece is the sum of:
- material: the weight of the blank (not the finished part—you pay for the chips) at the price per kilogram;
- machining: the time per workpiece for each phase, excluding setup time, based on the hourly cost of the machine and operator for that phase;
- Tools: as described in section 30.8;
- Setup: the setup cost divided by the number of workpieces in the batch;
- Overhead expenses: offices, design, quality control, warehousing, administration—in other words, everything that isn't tied to a machine. They are usually calculated as a percentage of machining operations costs.
Blank material: 166-mm-long piece of C45 with a diameter of 80 (density 7.85 g/cm³) at 1.80 €/kg. Sawing: 1.2 min at 35 €/h (saw plus operator). Turning: time per workpiece without setup 221.4 s (example 30.5) at Ch = 40.875 €/h. Tools 0.71 € (example 30.9). Setup 45 minutes. Overhead: 25% of costs for machining operations. Fictitious but realistic prices.
Material accounts for 70% of the cost: for a workpiece like this, reducing the length of the blank by 10 mm saves more than gaining 10 seconds in cycle time. If scrap chips are paid for, their value is subtracted from the cost of the material.
Same mandrel, 45-minute setup time (2,700 s, €30.66). How do the time per workpiece and cost per workpiece change for batches of 10, 100, and 1,000?
| Lot N | tatt / N (s) | tpz (s) | Time-based dimension fee | CPZ (€) |
|---|---|---|---|---|
| 10 | 270 | 491,4 | 54,9% | 16,70 + 3,83 = 20,53 |
| 100 | 27 | 248,4 | 10,9% | 16,70 + 0,38 = 17,08 |
| 1000 | 2,7 | 224,1 | 1,2% | 16,70 + 0,04 = 16,74 |
30.10 The Economic Lot
Looking at Figure 30.6, one might be tempted to produce huge batches. But workpieces made in advance remain in inventory: they take up space, tie up capital, and risk becoming useless if the drawing changes. The cost of holding inventory is usually estimated at between 15 and 25 percent per year of the workpiece’s value. There are therefore two costs pulling in opposite directions: with large batches, there are fewer production runs (fewer setups) but more inventory is held; with small batches, the opposite is true. The batch size that minimizes the sum is the economic batch size, given by Wilson’s formula (also known as Camp’s formula):
The customer picks up 2,400 pins per year on a regular basis. Launching a batch costs the setup fee (€30.66) plus €25 for administrative and inspection work; the annual maintenance cost is 20% of the cost of the workpiece (€16.89).
At the minimum, the launch cost and the maintenance cost are equal: this is a property of the formula. Furthermore, the curve is flat near the minimum, so you can round the lot size to a convenient number without losing almost anything.
November 30: Traditional Machine vs. CNC: The Break-Even Point
A simple workpiece can be made on a parallel lathe or a CNC lathe. The CNC lathe has a higher fixed cost per batch (the programs must be written and tested, and setup takes longer), but a much lower cost per workpiece, because it is faster and does not depend on the operator’s manual skill. The parallel lathe is the opposite. The cost of a batch of N workpieces is a straight line for each machine, and the two lines intersect at the break-even point.
Parallel lathe (fully depreciated): machine 8 €/h plus operator 22.50 €/h = 30.50 €/h; setup time 20 minutes; time per workpiece 11 minutes. CNC lathe: programming 1.5 hours at 45 €/h, setup 45 minutes at 40.875 €/h, machining cost per workpiece 2.514 € (example 30.10). Materials and tools are assumed to be the same and are not included in the calculation.
The bottom line changes if the program already exists (the batch is repeated and FCNC costs are reduced to just setup) or if the workpiece has profiles, cones, and radii that take much longer to machine by hand. On a CNC lathe, moreover, the quality remains consistent from the first workpiece to the last: this is an advantage that the cost analysis doesn’t show but that really matters.
12/30 The Budget
The estimate It is the price quoted to the customer before the work is done. It starts with the cost of the workpiece, then adds items specific to that order (scheduling, packaging, shipping, and any external machining operations such as heat treatment or galvanizing), and finally theuseful, the company's profit margin. A good estimate lists all the items: this way, you can see where you're making a profit and, if the customer asks for a discount, what you can negotiate.
A customer requests 50 bushings made of C45 steel: outer diameter 45, hole diameter 25, length 40 mm. They are machined on a CNC lathe from a 3-meter-long Ø50 bar, using a bar feeder in the turret: the machine feeds the bar automatically, and the operator unloads and inspects the workpieces while the machine is running (manual operations shown in gray). Each workpiece requires 47 mm of bar stock (40 mm for the workpiece, 1 mm for facing, 3 mm for trimming, and 3 mm for the final scrap that remains in the machine). Speed limit: 4,000 rpm. Fictitious but realistic data; hourly costs as shown in examples 30.7 and 30.8.
Cutting time, using the formulas in Chapter 26:
| Operation | Data | Time(s) |
|---|---|---|
| Full facing Ø50 (G96) | Vc 200, f 0.15, limit at Ø15.9 | 4,3 |
| Drilling, Ø24 (indexed insert drill bit) | Vc 150 → n 1989, f 0,1, L 48 | 14,5 |
| External roughing: Ø50 → Ø45.6 | Vc 220 → n 1536, f 0,3, L 46 | 6,0 |
| External finishing Ø45 | Vc 260 → n 1839, f 0,12, L 42 | 11,4 |
| Boring from Ø24 to Ø25 | Vc 180 → n 2292, f 0,1, L 42 | 11,0 |
| Cutting from Ø50 to Ø24 (G96) | Vc 120, f 0,06 | 12,6 |
| Cutting time | 59,8 | |
| Entry | € per workpiece | € for 50 workpieces |
|---|---|---|
| Material (C45 bar, Ø50) | 1,38 | 68,82 |
| CNC Lathe Machining | 0,98 | 48,76 |
| Setup and Programming | 1,72 | 85,88 |
| Tools | 0,35 | 17,52 |
| Overhead expenses (25%) | 0,76 | 38,04 |
| Packaging and Shipping | 0,50 | 25,00 |
| Full cost | 5,68 | 284,02 |
| Profit (12%) | 0,68 | 34,08 |
| Calculated price | 6,36 | 318,10 |
Here, the biggest cost factor isn't the material or the cut, but the setup costs associated with programming: for a batch of 500 bushings, the cost would drop to €0.17 per workpiece. That's why the quote always specifies the quantity for which the price applies.
30.13 Problems During Machining Operations: Causes and Solutions
When something goes wrong, the cutting edge and the chip almost always reveal why. The most common types of wear can be identified with the naked eye or with a magnifying glass:
| Problem | Probable cause | Remedy |
|---|---|---|
| Vibrations (noise, wavy surface) | Excessive tool or workpiece deflection; workpiece not clamped properly; nose radius too large; ap too small relative to the radius | Shorten the overhang; use a tailstock or steady rest; use a smaller nose radius, with κr close to 90°; adjust the spindle speed by 10–20%; increase the feed rate slightly |
| Rapid sidewall wear | Vc too high; grade too soft for the material; insufficient cooling | Lower Vc; use a more wear-resistant grade; check the coolant flow rate and concentration |
| Craterization (crater on the chest) | Temperature too high on the chest: Vc and high; coating not very suitable | Reduce Vc and then f; groove with an aluminum oxide coating; more positive geometry |
| Cutting edge (material bonded to the tip) | Vc too low; soft material (mild steel, stainless steel, aluminum); cutting edges not sharp enough | Increase Vc; sharp, positive cutting edge; coolant with more oil; for aluminum, uncoated polished inserts |
| Chips on the cutting edge | Impacts: interrupted cut, slag or sand in the stream; high feed at the inlet; material too hard and brittle; vibrations | Reduce f at the entry and exit points; use a steeper angle; reinforced cutting edge (chamfer); enter in an arc or with a fillet |
| Groove wear along the ap line | Materials that cause work hardening (stainless steel, superalloys) or a hard crust that always forms at the same point on the cutting edge | Vary the ap between passes; smaller κr (45°) or round insert; tougher grade |
| Deformed cutting edge (bends downward) | Temperature and pressure too high: Vc and f are excessive for the grade | Reduce Vc and f; harder grade; larger nose radius |
| Poor finishing | Feed rate too high for the nose radius; worn cutting edge; built-up edge; vibrations | Reduce f or use a larger radius or a wiper insert; change the cutting edge; increase Vc; eliminate vibrations |
| Long, tangled chips | Feed or ap too low for the chip breaker; incorrect chip breaker geometry | Increase f; ap must be at least equal to the nose radius; chipbreaker suitable for the machining operation; high-pressure coolant |
| Dimensions that vary with heating | Thermal expansion of the machine, workpiece, and tool during the first few hours of operation or after a shutdown; coolant that heats up | Machine warm-up cycle (15–20 min) before machining; measure the workpiece at room temperature; adjust the wear compensators through frequent checks; coolant at a constant temperature |
30.14 How to Improve a Cycle Time
Shortening the cycle time means producing more with the same machine and the same operator. Looking at Figure 30.3, it becomes clear that it’s not just about cutting speed. The main approaches are:
- fewer passes: use a larger ap during roughing, as long as the power and insert allow (example 30.1);
- higher feeds in finishing operations with wiper inserts, which, at the same level of roughness, operate at approximately twice the feed rate;
- G96 in facing (Example 26.9) and cutting speeds close to the maximum production speed (Chapter 24);
- shorter rapids: tool change points close to the workpiece, no unnecessary returns to the tool change point, tools in the turret arranged in order of use;
- Fewer tool changes: a single tool that performs multiple operations (for example, the same insert for facing and cylindrical turning);
- Manual operations in the background: bar loader or bar feeder, measurements taken while the machine is machining the next workpiece, in-machine probe;
- Shorter setup times (SMED, paragraph 30.5), which are more important when batch sizes are small.
Two changes are made to the spindle in Example 30.4 (cycle time = 201.3 s): the finishing operation switches to a wiper insert with f = 0.2 mm/rev instead of 0.1 (same speed, 1,284 rpm); the roughing passes are made 2 mm from the workpiece instead of moving away, and the rapid traverse times are reduced from 9 to 6 s.
To be on the safe side, a 15% reduction in the pin’s cycle time is factored in. How much is saved per workpiece, for a batch of 200 and 2,400 workpieces per year, with a 10% markup, Ch = 40.875 €/h, and 25% overhead? And how many additional workpieces are produced per shift?
30.15 The Formulas in This Chapter
| What Are You Looking For? | Formula | Units |
|---|---|---|
| Cutting time | tt = Σ L / vf | min |
| Time for the rapids | tr = Lr / vr | min |
| Machine time | tm = tt + tp | min or s |
| Cycle time | cycle = tm + tman (manual operations only when the machine is stopped) | min or s |
| Time per workpiece | tpz = tcycle · (1 + m) + tatt / N | min or s |
| OEE | OEE = D · E · Q | pure number |
| Depreciation | A = (V − Vr) / na | €/year |
| Interests | I = i · (V + Vr) / 2 | €/year |
| Hourly cost of the car | Cm = (A + I + S + Eel + M + Ug) / h | €/h |
| Operator's hourly rate | Co = Kaz / head | €/h |
| Hourly cost of the workstation | Ch = Cm + Co / k | €/h |
| Tool Cost per Workpiece | Cu = (Ct + ts · Ch) · tt / T | € |
| Unit Cost of a Workpiece | Cpz = Cmat + (Clav + Cu + Catt / N) · (1 + sg) | € |
| Economy Lot | Q* = √(2 · D · Cl / Cmag) | workpieces |
| Break-even point | Np = (FCNC − Ftrad) / (cv,trad − cv,CNC) | workpieces |
30.16 Exercises
Try to solve them on your own, using a calculator, before looking at the solution.
Solution
n = 220,000 / (3.1416 × 80) = 875 rpm; vf = 0.12 × 6 × 875 = 630 mm/min; L = 250 + 80 + 10 = 340 mm; t = 340 / 630 = 0.540 min = 32.4 s.
Solution
tcycle = 95 + 8 + 7.5 + 25 + 3 = 138.5 s; workpieces per hour = 3600 / 138.5 = 26.0.
Solution
138.5 · 1.12 = 155.1 s; setup time for a workpiece 3600 / 80 = 45 s; tpcs = 155.1 + 45 = 200.1 s = 3.34 min.
Solution
tpian = 440 min, tfunz = 390 min; D = 390 / 440 = 0.886; E = 330 · 1 min / 390 = 0.846; Q = 320 / 330 = 0.970; OEE = 0.886 × 0.846 × 0.970 = 0.727, approximately 73%.
Solution
A = 200,000 / 10 = 20,000 €; I = 0.04 · 120,000 = 4,800 €; S = 3,150 €; M = 6,600 €; Eel = 9 × 1,600 × 0.25 = 3,600 €; Ug = 3,000 €. Total: 41,150 €/year; Cm = 41,150 / 1,600 = 25.72 €/h.
Solution
Kaz = 29,000 × 1.36 = 39,440 €; Co = 39,440 ÷ 1,650 = 23.90 €/h.
Solution
Workpieces per cutting edge = 12 / 2.4 = 5. Unit price = 10 / 2 + 0.30 = 5.30 €; retainer = 1.5 / 60 · 42 = 1.05 €; Cu = (5.30 + 1.05) × 2.4 / 12 = 6.35 / 5 = 1.27 € per workpiece.
Solution
Np = (140 − 15) / (7.20 − 2.80) = 125 / 4.40 = 28.4: The CNC is cost-effective for 29 workpieces or more.
Solution
Cmag = 0.25 × 4 = 1 €/(workpiece · year); Q* = √(2 × 6,000 × 80 / 1) = √960,000 = 979.8, approximately 980 workpieces; runs = 6,000 / 980 = 6.1, which is practically 6 runs of 1,000 workpieces each.
Solution
Machining 2.5 / 60 · 40 = 1.667 €; setup 60 / 500 = 0.12 €; total machining operations costs 1.667 + 0.12 + 0.25 = 2.037 €; overhead 0.509 €; Cpz = 2.10 + 2.037 + 0.509 = 4.65 €.
Solution
30 s · 10,000 = 300,000 s = 83.3 h; savings of 83.3 · 45 = 3,750 € per year.
Solution
There are two problems. The glued material is causing a built-up edge, due to a cutting speed that is too low for mild steel: increase Vc to the values in the table (180–250 m/min with carbide) and use a sharp, positive-rake cutting edge. The whistling sound indicates vibration, because the shaft is long and thin: support it with the tailstock or a steady rest, use a small nose radius, and set κr close to 90°.