Chapter 30

Parameters, Timelines, and Costs

Knowing how to turn or mill isn’t enough: in the shop, you also need to know how long it takes to make a workpiece and how much it costs. In this chapter, we’ll outline the machining operations in a cycle, select the parameters using a systematic method, calculate the cycle time and the hourly machine cost, determine the cost of the workpiece and prepare a quote, and conclude by addressing the most common machining issues and ways to shorten cycle time.

30.1 The Machining Cycle

The machining cycle is the ordered list of all the steps involved in transforming the blank (a bar, a casting, a blank) into the finished part specified in the technical drawing. It is prepared by the engineering department or the production engineer before the batch enters the shop floor. The cycle is divided into three levels:

  • phase: everything that's done on the workpiece in the same machine or workstation (the saw, the lathe, the milling machine, the inspection station). The steps are numbered in increments of ten (10, 20, 30...), so a new step can be added without having to renumber everything;
  • sub-phase: the part of a phase consisting of a single placement, that is, without removing and re-mounting the workpiece. If the workpiece is rotated in the jaws halfway through a phase, a new sub-phase begins (20.1, 20.2...);
  • operation: a basic machining process performed with a single tool and the same parameters: facing, roughing, drilling (20.1.1, 20.1.2...).
cyclephasessub-phaseoperationsCycle for the Ø62 pinfrom blank to finished partPhase 10Cutting with a sawStep 20CNC turningStep 30Deburring and inspectionSub-step 20.1Clamping with jaws20.1.1facing20.1.2Roughing (3 passes)20.1.3finishing Ø62
Figure 30.1 · The pin cycle from Chapter 26 (Example 26.14): three phases, one subphase on the lathe, three operations.

The order of the steps is not random. The most common rules are: first, work on the surfaces that serve as reference As for the others, first... rough cut everything, and then yes ends (if heat treatment is involved, it comes in the middle: Chapter 22); dimensions subject to tight tolerances are produced in the same ranking, because every time you take the workpiece apart, you lose a little precision; you're looking for the fewer placements possible, because every placement takes time.

Production Schedule and Work Order for Machining Operations

The production cycle is documented in two documents. The production cycle sheet describes how the workpiece is made: for each phase and operation, it specifies the machine, the clamping equipment, the tool, the cutting parameters, and the estimated time, often accompanied by a small drawing of the phase. This is the technical document, which is the same for all batches of the same workpiece. Here is the process sheet for the C45 pin from Example 26.14 (bar Ø80, pin Ø62, 120 mm long, Ra 1.6 µm):

PhaseOperationMachine and OutletToolVc (m/min)n (rpm)f (mm/revolution)ap (mm)Time(s)
10Cutting a section Ø80 × 166Band saw, viseBimetal blade72
20.1.1Facing (1 mm)CNC lathe, chuck, 45 mmT0101 rhombic 80°, rε 1.2180 (G96)716-40000,218,7
20.1.2Roughing: Ø80 → Ø62.6 in 3 passesas aboveT0101200858-10170,32,978,6
20.1.3Finishing Ø62as aboveT0303 rhombic 55°, rε 0.825012840,10,357,0
30Deburring, Ø62 and Ra inspectionTest Bench50-75 Micrometer, Roughness Testeron a sample basis

The machining order (or phase sheet), on the other hand, is the document that accompanies the batch in the workshop. It specifies which batch it is, how many workpieces there are, which phase is being carried out, and records what actually happens: who worked on it, how long it took, how many good workpieces, and how many rejects. It is used for traceability (if a workpiece breaks at the customer’s site, it is possible to trace it back to the batch, the machine, and the operator) and for performance analysis—that is, comparing planned times with actual times. Here is an example filled out for stage 20 of the pin:

Production OrderOP 2026/0418Code and DrawingPRN-062 Rev. B
DescriptionPin Ø62 × 120MaterialDrawn C45, Ø80
Lot Quantity200 workpiecesPhase20 · CNC turning
MachineCNC Lathe No. 3ProgramO2062
Planned Equipment45 minEstimated time per workpiece221.4 s (Example 30.5)
DateOperatorSetup (h)Hours workedGood WorkpiecesWasteNotes
16/11G. R.0,86,59722 workpieces, Ø62, below tolerances on first startup
17/11G. R.06,41010closed lot
Total0,812,91982Check: Phase 30

The worksheet immediately shows that the actual setup time (0.8 h, or 48 minutes) was slightly longer than expected and that two good workpieces are missing: the supervisor decides whether to rework them or ship 198 as agreed with the customer.

30.2 Selecting Parameters Step by Step

Cutting parameters aren't chosen at random, and they aren't all chosen at once. You follow a specific order, because each choice limits the next one:

  • Material and ISO group: Identify the material from the drawing and place it in its corresponding group (P for steels, M for stainless steels, K for cast iron, N for non-ferrous metals, S for superalloys and titanium, H for hardened steels: Chapters 24 and 25);
  • Tool: insert shape and size, nose radius, chipbreaker, and grade suitable for the assembly and the machining operations;
  • pass depth ap: the largest size that the workpiece, the insert, and the machine can handle, so fewer passes are needed;
  • feed rate f: the highest rate compatible with the chipbreaker, the strength of the cutting edge, and, for finishing operations, the required roughness;
  • cutting speed Vc: finally, refer to the supplier’s table, because it determines the life of the cutting edge (Taylor’s Law and the minimum-cost speed are discussed in Chapter 24);
  • Checks: Calculate revolutions, feed rate, force, and power (Chapter 26), as well as the theoretical roughness; if something doesn't add up, go back and correct it.
Drawing: Material, Dimensions, RoughnessISO material group (P, M, K, N, S, H)Tool: insert shape, insert radius rε, gradeap: the largest value that the workpiece and machine can handlef: the highest value permitted by the chip and roughnessVc: from the table, selected for tool lifeCalculation of n, vf, Fc, and PmIs Pm ≤ machine power?YesTheoretical Ra ≤ Ra specified in the drawing?YesProgram, test on the workpiece, correctionNoReduce f,then ap or Vcnoreduce f or increaserε (wiper insert)
Figure 30.2 · Selecting the parameters. If the power is insufficient, reduce the feed rate first; if the roughness is not acceptable, adjust the feed rate or the nose radius.
Example 30.1 · Selecting Parameters for a Shaft Made of 42CrMo4

A quenched and tempered 42CrMo4 steel shaft is to be turned from Ø70 to Ø60 over a length of 150 mm, with a surface roughness of Ra 3.2 µm. The lathe has a 7.5 kW motor with an efficiency of 0.8. An 80° rhombic insert with rε = 0.8 mm and κr = 95° is used, cutting to a depth of up to 4 mm; for this material, kc1 = 2000 N/mm² and mc = 0.25.

ISO group: P, quenched and tempered alloy steel → from Table 26.12: Vc 140–200 m/min, f 0.2–0.4 mm/rev, ap 1.5–5 mm
material on the radius = (70 − 60) / 2 = 5 mm; 0.5 mm is left for finishing → 4.5 mm to be rough-machined
ap: 4.5 / 4 = 1.1 → 2 passes of 2.25 mm (Ø70 → Ø65.5 → Ø61)
First test: f = 0.35 mm/revolution, Vc = 180 m/min
h = 0.35 · sin 95° = 0.349 mm → kc = 2000 / 0.3490.25 = 2000 / 0.7684 = 2603 N/mm²
Fc = 2603 × 2.25 × 0.35 = 2050 N → Pc = 2050 × 180 / 60,000 = 6.15 kW → Pm = 6.15 / 0.8 = 7.69 kW > 7.5 kW ✗
Second test: feed rate is reduced to f = 0.3 mm/revolution
h = 0.299 mm → kc = 2000 / 0.7394 = 2705 N/mm² → Fc = 2705 · 2.25 · 0.3 = 1826 N
Pc = 1,826 × 180 / 60,000 = 5.48 kW → Pm = 5.48 / 0.8 = 6.85 kW < 7.5 kW ✓
Roughness of the roughing pass: Ra = 0.3² · 1000 / (31.2 × 0.8) = 90 / 24.96 = 3.61 µm > 3.2 → a finishing pass is required ✓ (as planned)
finishing (ap = 0.5 mm): fmax = √(31.2 · 0.8 · 3.2 / 1000) = 0.283 mm/revolution → f = 0.2 is chosen (theoretical Ra 1.60 µm, half the limit)
RPM: roughing n = 180,000 / (3.1416 × 65.5) = 875 and 180,000 / (3.1416 × 61) = 939 rpm; finishing with Vc = 240: n = 240,000 / (3.1416 × 60) = 1,273 rpm
Roughing: 2 passes at 2.25 mm, f 0.3, Vc 180 (6.85 kW). Finishing: ap 0.5, f 0.2, Vc 240.

30.3 Initial Parameters for Turning, Milling, and Drilling

The table compiles the starting values for the three most common machining operations, by ISO group, in a single location. For turning, these are the roughing values from Table 26.12 (which also includes finishing values); for milling, the values refer to coated carbide-tipped end mills for face milling and contouring (Chapter 27), with the feed per tooth (fz); for drilling, solid carbide drills with diameters ranging from 8 to 12 mm (Chapter 28).

ISO Group and MaterialTurning (roughing)MillingDrilling
Vc (m/min)f (mm/revolution)Vc (m/min)fz (mm/tooth)Vc (m/min)f (mm/revolution)
P · non-alloy steel (C40, C45)180-2500,25-0,5180-2800,1-0,2580-1200,15-0,3
P · quenched and tempered alloy steel140-2000,2-0,4150-2200,1-0,270-1000,12-0,25
M · austenitic stainless steel120-1800,15-0,35120-1800,08-0,1540-700,08-0,18
K · gray cast iron160-2500,2-0,5150-2500,1-0,2580-1300,2-0,35
N · aluminum alloys300-8000,2-0,5400-12000,08-0,2150-3000,2-0,4
N · brass200-4000,15-0,4200-4000,08-0,2100-2000,15-0,3
S · titanium (Ti6Al4V)40-700,1-0,340-700,05-0,1225-450,08-0,15
S · nickel superalloys25-500,1-0,2525-450,05-0,115-300,05-0,12
H · Hardened steel, 55–60 HRC80–150 (CBN)0,05-0,280-1500,05-0,130-600,05-0,12

A guideline table prepared by CNC Simulator Italia, with rounded average values, for training purposes and for the first workpiece. The correct values for a specific tool are provided by its supplier. With high-speed steel (HSS) tools, cutting speeds drop to about one-third for drilling and to one-fifth or less for turning and milling.

💡
The starting point is not the end point. The first workpiece is machined using values in the middle of the range; then you examine the chip, listen to the machine, measure the surface, and check for wear after a certain number of workpieces. If everything goes well, move toward the upper end of the range; if any of the problems described in paragraph 30.13 arise, correct them as indicated there.

30.4 Machining Times

The time that passes between one workpiece and the next is made up of different workpieces, and it’s best to call them by their proper names:

  • cutting time (or active time): the tool is in the material and is removing chips. It is calculated using the formulas in Chapters 26, 27, and 28;
  • Passive times: the machine moves but does not cut. These include rapid movements (G00) to approach and retract, returns to the start of the pass, tool changes, spindle start and stop, and range changes;
  • machine time: the sum of the two, that is, the time the program runs;
  • Manual operations: tasks performed by the operator, such as loading and unloading the workpiece, cleaning the jaws, and taking measurements. If these are performed while the machine is stopped, they are added to the machine time; if they are performed while the machine is running (for example, measuring the previous workpiece), they are referred to as shadow time and do not extend the cycle time;
  • cycle time: the time between the release of one workpiece and the release of the next.
Cutting time, idle time, machine time, and cycle time
tt = Σ Lvf tr = Lrvr tm = tt + tp
tcycle = tm + tman
tt cutting time, sum of the working travels L (mm) divided by their feed rate vf (mm/min) · tr rapid traverse time · Lr distance traveled during rapid traverse in mm · vr average rapid traverse speed in mm/min, lower than the rated speed due to acceleration and deceleration · tp passive times (rapid traverse, tool changes, spindle) · tm machine time · tman manual times performed while the machine is stopped · all times in the same unit (minutes or seconds)
Example 30.2 · Cutting time for a face milling operation

A 300-mm-long C45 plate is machined flat using a 5-tooth Ø63 insert-tipped end mill, with Vc = 200 m/min and fz = 0.15 mm/tooth. The end mill passes through the center of the workpiece and must exit completely; add 3 mm of approach and 3 mm of exit (the calculation of the milling travel is explained in Chapter 27).

n = 1000 · 200 / (3.1416 · 63) = 1010.5 → 1010 rpm
vf = fz · z · n = 0.15 · 5 · 10¹⁰ = 757.5 mm/min
L = 300 + 63 + 3 + 3 = 369 mm
tt = 369 / 757.5 = 0.487 min = 0.487 × 60 = 29.2 s
tt ≈ 29 s for the leveling pass
Example 30.3 · When passive tenses take their toll: eight holes

On a machining center, 8 holes with a diameter of 10 and a depth of 20 mm are drilled into a C45 plate. First, the workpiece is centered using a center drill (1,500 rpm, f = 0.1 mm/rev, travel 3 + 2 = 5 mm), then holes are drilled using a carbide drill bit (Vc = 90 m/min, f = 0.2 mm/rev). The drilling travel is 20 mm plus the tapered drill (approximately 0.3 × D = 3 mm) plus 2 mm of approach. Each movement from one hole to the next, including rapid ascent and descent, takes 1.0 s; each tool change, from chip to chip, takes 5 s.

centering: vf = 0.1 × 1500 = 150 mm/min → t = 5 / 150 = 0.0333 min = 2.0 s per hole → 8 × 2.0 = 16.0 s
Drilling: n = 1000 · 90 / (3.1416 · 10) = 2865 rpm → vf = 0.2 · 2865 = 573 mm/min
L = 20 + 3 + 2 = 25 mm → t = 25 / 573 = 0.0436 min = 2.62 s per hole → 8 × 2.62 = 20.9 s
cutting time: 16.0 + 20.9 = 36.9 s
Passive times: tool movements 2 tools × 8 = 16 movements × 1.0 = 16 s; tool changes 2 × 5 = 10 s → 26 s
machine time: 36.9 + 26 = 62.9 s; passive dimension = 26 / 62.9 = 0.413
tm ≈ 63 s, of which 41% is chip-free

For workpieces that require many small machining operations, non-cutting times can account for nearly as much of the total time as the cutting time itself: to shorten the cycle time, it is more effective to reduce movements and tool changes than to increase the cutting speed.

Example 30.4 · The Key Concept of Chapter 26: From Cutting Time to Cycle Time

In Example 26.14, the pin has a cutting time of 144.3 s (facing 8.65 s, roughing 78.6 s, finishing 57.0 s). Now let’s add the rest, using these shop floor data (fictitious but realistic): throughout the program, the turret travels 1,500 mm in rapid traverse at an average speed of 10 m/min, including acceleration and deceleration; there are 2 tool changes (T0101 → T0303 and back) taking 3 s each; the spindle starts and stops once, taking 2 s per operation; Manual loading and unloading of the workpiece, with the machine stopped, takes 30 s; one out of every five workpieces is measured on the machine with a micrometer, taking 40 s.

rapid feed: vr = 10,000 mm/min = 166.7 mm/s → tr = 1,500 / 166.7 = 9.0 s
Tool changes: 2 × 3 = 6 s · Spindle: 2 × 2 = 4 s
Passive times: tp = 9.0 + 6 + 4 = 19.0 s
machine time: tm = 144.3 + 19.0 = 163.3 s
Manual cycle times: 40 / 5 = 8 s per workpiece → tman = 30 + 8 = 38 s
cycle time: tcycle = 163.3 + 38 = 201.3 s = 3.36 min
cycle = 201.3 s: cutting accounts for 71.7%, idle time for 9.4%, and manual labor for 18.9%
Cutting time144.3 sRapid movements and approaches9.0 sTool change6.0 sSpindle start and stop4.0 sLoading and unloading30.0 sMeasurement (1 out of 5 workpieces)8.0 sCycle time 201.3 sCutting 144.3 s (71.7%)Idle time 19.0 s (9.4%)Manual 38.0 s (18.9%)
Figure 30.3 · The cycle time of the pin, broken down by item (top) and grouped (bottom). More than a quarter of the time is spent without chip removal.

30.5 Setup, surcharges, and time per workpiece

Before machining the first workpiece of a batch, the machine must be set up: the correct jaws are installed, the tools and program are loaded, the offsets are measured, the origin is set, the first workpiece is machined, and it is inspected. This time, tatt, is spent once per batch and must be divided among the N workpieces in the batch.

Then there's the fact that no one works eight hours straight at the same pace. The measured or calculated time is increased by applying percentage-based adjustments:

  • the rest factor (or from fatigue): recovery after heavy, repetitive work or work in a hot and noisy environment;
  • the physiological factor: personal needs (drinking, using the restroom), which cannot be eliminated;
  • often a small dimension set aside for unexpected expenses (a chip to remove, an extra check).

In machine shops, the total is usually between 5 and 15 percent. Here, the surcharge applies to the entire cycle time, because on a lathe without a feeder, when the operator stops, the machine stops as well.

Time per workpiece
tpcs = tcycle · (1 + m) + tattN
tpz: time per workpiece · tciclo: cycle time · m: total markup expressed as a decimal (10% = 0.10) · tatt: batch setup time · N: number of workpieces in the batch · times in the same unit
Example 30.5 · Time per workpiece and workpieces per shift

The pin in Example 30.4 (cycle time = 201.3 s) is produced in a batch of 200 workpieces. Setup takes 45 minutes, and the markup is 10%. What is the time per workpiece, and how many workpieces are produced in an 8-hour shift?

normalized time: 201.3 × 1.10 = 221.4 s
Setup time for a workpiece: 45 · 60 / 200 = 2,700 / 200 = 13.5 s
tpz = 221.4 + 13.5 = 234.9 s = 3.92 min
workpieces per shift: 8 · 3,600 / 234.9 = 28,800 / 234.9 = 122.6 → 122 workpieces
tpz ≈ 235 s; about 122 workpieces per shift, so a batch of 200 keeps the machine busy for a little over one and a half shifts
🔧
Single-Minute Exchange of Die (SMED). This is the name of the method used to shorten setup times: operations that can be performed while the machine is still running (setting up jaws and tools, presetting tools off the machine, having the program already tested on the simulator) are separated from those that require the machine to be stopped, and as many tasks as possible are moved into the first group. Reducing setup time from 45 to 20 minutes makes it cost-effective to work in small batches.

30.6 Plant Performance (OEE)

A machine may appear fast on paper but actually produce very little in reality—because it is idle due to breakdowns and setup times, because it operates more slowly than expected, or because it produces scrap. OEE (Overall Equipment Effectiveness) combines these three types of losses into a single figure:

  • Availability D: the portion of scheduled time during which the machine actually operated (excluding breakdowns, setup times, and waiting for materials);
  • Efficiency E (or performance): the amount produced compared to what would have been produced in the expected cycle time (slowsdowns, micro-stops, and reduced feeds set with the selector are not accounted for);
  • Quality Q: the proportion of produced workpieces that are good (excluding scrap and workpieces requiring rework).
OEE
OEE = D · E · Q
D = tfunztflat E = Nprod · tcycletfunz Q = NgoodNprod
tpian: planned production time (shift minus scheduled breaks) · tfunz: time the machine was in operation · Nprod: number of workpieces produced · Nbuoni: number of good workpieces · tciclo: planned cycle time · D, E, Q, and OEE are numbers between 0 and 1, often expressed as percentages
Example 30.6 · The OEE for one shift on the pin lathe

An 8-hour shift with a scheduled 30-minute break. During the shift: 45 minutes of setup, a 20-minute breakdown of the coolant system. A total of 100 pins were produced (cycle time = 201.3 s), of which 3 were rejected.

tpian = 480 − 30 = 450 min · tfunz = 450 − 45 − 20 = 385 min
D = 385 / 450 = 0,856
Time required: 100 · 201.3 / 60 = 335.5 min → E = 335.5 / 385 = 0.871
Q = 97 / 100 = 0,970
OEE = 0.856 × 0.871 × 0.970 = 0.723
OEE ≈ 72%: Of the 450 paid minutes, only 325 resulted in good workpieces

Verification: 97 good workpieces · 201.3 s = 325.4 min, and 325.4 / 450 = 0.723. In theory, with an OEE of 1, 450 · 60 / 201.3 = 134 good pins would have been produced in 450 minutes.

450 minplanned385 minOperating−65 min · D = 85.6%335.5 minNet productive time−49.5 min · E = 87.1%325.4 minYield (good workpieces)−10.1 min · Q = 97.0%OEE = 325.4 / 450 = 72.3%
Figure 30.4 · From scheduled time to actual time: each bar loses a workpiece (red dashed line). The ratio between two adjacent bars is D, then E, then Q.

As a general rule of thumb, many workshops fall between 50 and 65 percent; 85 percent is considered an excellent result. Knowing the three separate figures is more useful than the final number: it indicates where to take action (fewer breakdowns, faster setup times, fewer micro-stops, less scrap).

30.7 The hourly cost of machinery and labor

To find out how much a workpiece costs, you need to know how much an hour of machine time costs. The hourly cost of the machine takes all the expenses the machine incurs in a year and divides them by the number of hours it operates:

  • depreciation: the loss in value of the machine, spread over its useful life;
  • interest: the cost of the money invested in the machine (if borrowed, the interest paid to the bank; if it is the owner’s own money, the return it would have earned elsewhere), calculated on the average capital tied up;
  • space: the dimension of the rent, heating, and lighting costs for the warehouse based on the square meters occupied (machine plus work area);
  • energy: electricity consumption, with the average power draw much lower than the installed capacity;
  • maintenance: routine and major, usually estimated as a percentage of the price;
  • General tools and consumables: tool holders, jaws, coolant, oil, filters. The inserts, which depend on the workpiece, are counted separately (section 30.8).
Items in the machine's hourly cost
A = V − Vrna I = i · V + Vr2 Eel = Pmed · h · ckWh
Cm = A + I + S + Eel + M + Ugh
V price of the installed machine in € · Vr residual value at end of life in € · na years of useful life · i annual interest rate (4% = 0.04) · Pmed average power consumption in kW · h operating hours per year · ckWh energy price in €/kWh · S space cost · M maintenance · Ug general tools and supplies · all items in € per year · Cm hourly cost of the machine in €/h
Example 30.7 · The hourly cost of a CNC lathe

Fictitious but realistic data for a medium-sized CNC lathe in 2026: installed price €150,000, useful life 10 years, residual value €15,000; interest rate of 4%; occupies 30 m² at €90/m² per year; maintenance costs 3% of the price per year; average power consumption 7 kW (installed capacity 22 kW), electricity at 0.25 €/kWh; general tooling and consumables 2,600 € per year; one shift, 1,600 hours of actual work per year.

Depreciation: A = (150,000 − 15,000) / 10 = 13,500 €/year
Interest: I = 0.04 · (150,000 + 15,000) / 2 = 0.04 · 82,500 = 3,300 €/year
space: S = 30 × 90 = 2,700 €/year
maintenance: M = 0.03 × 150,000 = 4,500 €/year
energy: Eel = 7 × 1,600 × 0.25 = 2,800 €/year
Tools and supplies: Ug = 2,600 €/year
Total: 13,500 + 3,300 + 2,700 + 4,500 + 2,800 + 2,600 = 29,400 €/year
Cm = 29 400 / 1600 = 18,375 €/h
Cm ≈ 18.38 €/h; nearly half of that is depreciation
Depreciation13,500 € · 45.9%Maintenance4,500 € · 15.3%Interest on principal€3,300 · 11.2%Electricity€2,800 · 9.5%Space occupied€2,700 · 9.2%Tools and supplies2,600 € · 8.8%Total: 29,400 € per year / 1,600 hours = 18.38 €/h
Figure 30.5 · The components of the annual cost of the lathe in Example 30.7. The first three do not depend on the amount of work performed: with two shifts, the hourly cost drops significantly.

Labor costs are calculated in the same way: the company’s annual cost for the employee (gross salary plus social security contributions, severance pay, and insurance) divided by the actual hours worked, which are fewer than the hours paid due to vacation, holidays, time off, and sick leave.

Hourly cost of labor and workstation
Co = Kazhlav Ch = Cm + Cok
Co Operator's hourly rate in €/h · Kaz Annual business cost in € · hlav hours worked per year · Ch Hourly cost for both the machine and the operator · k number of machines monitored by the same operator (1 if only one is monitored)
Example 30.8 · How much does one hour of lathe time cost, including the operator?

The operator costs the company €37,800 per year (approximately €27,600 gross plus €10,200 in social security contributions, severance pay, and insurance) and works 1,680 actual hours. Calculate the hourly cost of the operator and that of the lathe plus the operator; then recalculate the cost if the same operator operates two identical lathes.

Co = 37 800 / 1680 = 22,50 €/h
a lathe: Ch = 18.375 + 22.50 = 40.875 €/h ≈ 40.88 €/h
two lathes: Ch = 18.375 + 22.50 / 2 = 18.375 + 11.25 = 29.625 €/h ≈ 29.63 €/h
Ch = 40.88 €/h with one operator per machine; 29.63 €/h when operating two

In the following examples, Ch is set to 40.875 €/h, which is 40.875 / 3600 = 0.01135 € per second.

30.8 Tooling Cost per Workpiece

A cutting edge lasts for a certain cutting time T (its service life, which depends primarily on the cutting speed: Taylor’s law, Chapter 24), after which it must be turned or replaced. The cost of a cutting edge includes its price (the price of the insert divided by the number of usable cutting edges), a portion of the tool holder’s cost—which lasts for a few hundred cutting edges—and the cost of the time the machine is idle during replacement. This cost is spread across the workpieces that the cutting edge is able to produce.

Tooling Cost per Workpiece
Ct = Pinszt + qp Cu = (Ct + ts · Ch ) · ttT
Ct Cost of a cutting edge in € · Pins Price of the insert in € · zt usable cutting edges of the insert · qp Tool holder dimension for cutting edge in € · Cu Tool cost per workpiece in € · ts Cutting edge replacement time in hours · Ch Hourly cost of machine and operator in €/h · tt Cutting time for that tool on a workpiece · T cutting edge life · tt and T in the same unit; T / tt This is the number of workpieces per cutting edge
Example 30.9 · How much do the pin inserts cost?

Roughing and facing with T0101: 12 € insert with 4 cutting edges, tool holder dimension 0.40 € per cutting edge, tool life T = 15 min, cutting time per workpiece 8.65 + 78.6 = 87.25 s. Finishing with T0303: €14 insert with 4 cutting edges, same tool holder dimension, T = 20 min, cutting time 57.0 s. Replacing a cutting edge stops the machine for 2 minutes; Ch = €40.875/h.

Downtime cost: ts · Ch = (2 / 60) · 40.875 = 1.36 €
Roughing: Ct = 12 / 4 + 0.40 = 3.40 € · tt = 87.25 / 60 = 1.454 min · workpieces per cutting edge = 15 / 1.454 = 10.3
Cu = (3,40 + 1,36) · 1,454 / 15 = 4,76 · 0,0969 = 0,46 €
finishing: Ct = 14 / 4 + 0.40 = 3.90 € · tt = 57.0 / 60 = 0.95 min · workpieces per cutting edge = 20 / 0.95 = 21.1
Cu = (3,90 + 1,36) · 0,95 / 20 = 5,26 · 0,0475 = 0,25 €
Tool cost ≈ 0.46 + 0.25 = 0.71 € per pin

Increasing the cutting speed reduces cutting time, but the tool life (T) decreases much more: beyond a certain point, the cost of the inserts increases more than the time saved. The “minimum-cost speed” discussed in Chapter 24 indicates where the balance lies.

30.9 The cost per workpiece

Now all the workpieces on the bill are listed. The cost of a workpiece is the sum of:

  • material: the weight of the blank (not the finished part—you pay for the chips) at the price per kilogram;
  • machining: the time per workpiece for each phase, excluding setup time, based on the hourly cost of the machine and operator for that phase;
  • Tools: as described in section 30.8;
  • Setup: the setup cost divided by the number of workpieces in the batch;
  • Overhead expenses: offices, design, quality control, warehousing, administration—in other words, everything that isn't tied to a machine. They are usually calculated as a percentage of machining operations costs.
Unit Cost of a Workpiece
Cpz = Cmat + (Clav + Cu + CattN) · (1 + sg)
Cpz: unit cost in € · Cmat: blank material cost · Clav = tpz · Ch: machining cost for all stages (where tpz excludes setup costs) · Cu: tooling cost · Catt = tatt · Ch: setup cost · N: number of workpieces in the batch · sg: percentage of overhead as a decimal
Example 30.10 · The cost of a pin in a batch of 200

Blank material: 166-mm-long piece of C45 with a diameter of 80 (density 7.85 g/cm³) at 1.80 €/kg. Sawing: 1.2 min at 35 €/h (saw plus operator). Turning: time per workpiece without setup 221.4 s (example 30.5) at Ch = 40.875 €/h. Tools 0.71 € (example 30.9). Setup 45 minutes. Overhead: 25% of costs for machining operations. Fictitious but realistic prices.

volume: V = 3.1416 · 80² / 4 · 166 = 834,407 mm³ = 834.4 cm³ → mass = 834.4 · 7.85 = 6,550 g = 6.55 kg
materials: 6.55 × 1.80 = 11.79 €
Note: 1.2 / 60 · 35 = 0.70 €
turning: 221.4 / 3,600 · 40.875 = 2.51 €
Setup: 0.75 h · 40.875 = 30.66 € → per workpiece 30.66 / 200 = 0.15 €
machining costs: 0.70 + 2.514 + 0.712 + 0.153 = 4.079 ≈ 4.08 € → overhead costs 0.25 × 4.08 = 1.02 €
Cpz = 11.79 + 4.08 + 1.02 = 16.89 €
The pin costs about €16.89; a batch of 200 costs about €3,378

Material accounts for 70% of the cost: for a workpiece like this, reducing the length of the blank by 10 mm saves more than gaining 10 seconds in cycle time. If scrap chips are paid for, their value is subtracted from the cost of the material.

Example 30.11 · How much does setup time amount to for lot sizes of 10, 100, and 1,000?

Same mandrel, 45-minute setup time (2,700 s, €30.66). How do the time per workpiece and cost per workpiece change for batches of 10, 100, and 1,000?

Fixed portion of the cost, excluding setup: 11.79 + (0.70 + 2.514 + 0.712) × 1.25 = 16.70 €
Setup costs including overhead: 30.66 × 1.25 = 38.32 € per batch
Lot Ntatt / N (s)tpz (s)Time-based dimension feeCPZ (€)
10270491,454,9%16,70 + 3,83 = 20,53
10027248,410,9%16,70 + 0,38 = 17,08
10002,7224,11,2%16,70 + 0,04 = 16,74
With 10 workpieces, more than half the time is spent on setup; with 1,000 workpieces, it hardly matters anymore
1020304050601101001,000Lot of 10: 20.53 €Lot of 200: 16.89 €without setup: 16.70 €1 workpiece: 55.02 €€ per workpieceworkpieces per lot (logarithmic scale)
Figure 30.6 · Cost per pin as the lot size varies. The curve drops rapidly and then levels off along the green line: beyond a few hundred workpieces, increasing the lot size yields almost no further savings.

30.10 The Economic Lot

Looking at Figure 30.6, one might be tempted to produce huge batches. But workpieces made in advance remain in inventory: they take up space, tie up capital, and risk becoming useless if the drawing changes. The cost of holding inventory is usually estimated at between 15 and 25 percent per year of the workpiece’s value. There are therefore two costs pulling in opposite directions: with large batches, there are fewer production runs (fewer setups) but more inventory is held; with small batches, the opposite is true. The batch size that minimizes the sum is the economic batch size, given by Wilson’s formula (also known as Camp’s formula):

Economy Lot (Wilson)
Q* = √2 · D · ClCmag
annual cost = DQ · Cl + Q2 · CMay
Q* Economy pack (loose workpieces) · D number of workpieces requested in a year · Cl Launch cost for a batch in € (tooling plus order, documentation, first-workpiece inspection) · CMay Annual maintenance cost per workpiece in € · Q / 2 is the average inventory level if workpieces leave the warehouse on a regular basis
Example 30.12 · The Economic Lot Size for the Pin

The customer picks up 2,400 pins per year on a regular basis. Launching a batch costs the setup fee (€30.66) plus €25 for administrative and inspection work; the annual maintenance cost is 20% of the cost of the workpiece (€16.89).

Cl = 30.66 + 25 = 55.66 € · Cmag = 0.20 · 16.89 = 3.378 €/(workpiece · year)
Q* = √(2 × 2,400 × 55.66 / 3.378) = √79,093 = 281.2 workpieces
pitches per year: 2,400 / 281.2 = 8.5
minimum annual cost: 2,400 / 281.2 · 55.66 + 281.2 / 2 · 3.378 = 475.0 + 475.0 = 949.9 €
Basically, you choose a batch of 300 (8 rolls): 8 × 55.66 + 150 × 3.378 = 445.3 + 506.7 = 951.9 €
Q* ≈ 281 workpieces; with batches of 300, you spend just €2 more per year

At the minimum, the launch cost and the maintenance cost are equal: this is a property of the formula. Furthermore, the curve is flat near the minimum, so you can round the lot size to a convenient number without losing almost anything.

5001,0001,5002,0001002003004005006007000Minimum: Q* ≈ 281 workpieces, approximately 950 € per yeartotal costmaintenanceLaunch cost€ per yearworkpieces per batch Q
Figure 30.7 · Launch costs decrease with batch size, while maintenance costs rise in a straight line; the sum reaches its minimum where the two curves intersect.

November 30: Traditional Machine vs. CNC: The Break-Even Point

A simple workpiece can be made on a parallel lathe or a CNC lathe. The CNC lathe has a higher fixed cost per batch (the programs must be written and tested, and setup takes longer), but a much lower cost per workpiece, because it is faster and does not depend on the operator’s manual skill. The parallel lathe is the opposite. The cost of a batch of N workpieces is a straight line for each machine, and the two lines intersect at the break-even point.

Tie between two cars
C (N ) = F + cv · N Np = FCNC − Ftradcv,trad − cv,CNC
C(N) lot cost in € · F fixed cost per lot (planning and setup) in € · cv variable cost per workpiece in € · Np number of workpieces beyond which it is more cost-effective to use the machine with the higher fixed cost
Example 30.13 · The Pin: Conventional Lathe or CNC?

Parallel lathe (fully depreciated): machine 8 €/h plus operator 22.50 €/h = 30.50 €/h; setup time 20 minutes; time per workpiece 11 minutes. CNC lathe: programming 1.5 hours at 45 €/h, setup 45 minutes at 40.875 €/h, machining cost per workpiece 2.514 € (example 30.10). Materials and tools are assumed to be the same and are not included in the calculation.

Traditional: F = 20 / 60 · 30.50 = 10.17 € · cv = 11 / 60 · 30.50 = 5.592 €
CNC: F = 1.5 × 45 + 30.66 = 67.50 + 30.66 = 98.16 € · cv = 2.514 €
Np = (98.16 − 10.17) / (5.592 − 2.514) = 87.99 / 3.078 = 28.6 workpieces
Check for 28.6 workpieces: 10.17 + 5.592 × 28.6 = 170.0 € and 98.16 + 2.514 × 28.6 = 170.0 €
Batch of 200: Traditional 10.17 + 5.592 × 200 = 1,128.5 € · CNC 98.16 + 2.514 × 200 = 601.0 €
For up to 28 workpieces, a parallel lathe is the better choice; for 29 or more, a CNC machine is better; for 200 workpieces, a CNC machine saves about €527
501001502002503003500102030405060Draw: 28.6 workpieces, 170 €parallel latheCNC lathebatch cost (€)Number of workpieces in batch N
Figure 30.8 · Lot cost as a function of the number of workpieces. The CNC curve starts higher but rises more gradually: to the left of the break-even point, the parallel lathe is more cost-effective; to the right, the CNC machine is.

The bottom line changes if the program already exists (the batch is repeated and FCNC costs are reduced to just setup) or if the workpiece has profiles, cones, and radii that take much longer to machine by hand. On a CNC lathe, moreover, the quality remains consistent from the first workpiece to the last: this is an advantage that the cost analysis doesn’t show but that really matters.

12/30 The Budget

The estimate It is the price quoted to the customer before the work is done. It starts with the cost of the workpiece, then adds items specific to that order (scheduling, packaging, shipping, and any external machining operations such as heat treatment or galvanizing), and finally theuseful, the company's profit margin. A good estimate lists all the items: this way, you can see where you're making a profit and, if the customer asks for a discount, what you can negotiate.

Example 30.14 · Quote for 50 bushings

A customer requests 50 bushings made of C45 steel: outer diameter 45, hole diameter 25, length 40 mm. They are machined on a CNC lathe from a 3-meter-long Ø50 bar, using a bar feeder in the turret: the machine feeds the bar automatically, and the operator unloads and inspects the workpieces while the machine is running (manual operations shown in gray). Each workpiece requires 47 mm of bar stock (40 mm for the workpiece, 1 mm for facing, 3 mm for trimming, and 3 mm for the final scrap that remains in the machine). Speed limit: 4,000 rpm. Fictitious but realistic data; hourly costs as shown in examples 30.7 and 30.8.

Cutting time, using the formulas in Chapter 26:

OperationDataTime(s)
Full facing Ø50 (G96)Vc 200, f 0.15, limit at Ø15.94,3
Drilling, Ø24 (indexed insert drill bit)Vc 150 → n 1989, f 0,1, L 4814,5
External roughing: Ø50 → Ø45.6Vc 220 → n 1536, f 0,3, L 466,0
External finishing Ø45Vc 260 → n 1839, f 0,12, L 4211,4
Boring from Ø24 to Ø25Vc 180 → n 2292, f 0,1, L 4211,0
Cutting from Ø50 to Ø24 (G96)Vc 120, f 0,0612,6
Cutting time59,8
Passive cycle times: rapid movement 6 s + 5 tool changes at 2 s each + bar feed 6 s = 22 s
cycle time: 59.8 + 22 = 81.8 s (manual times are shaded)
The increase is reduced to 5% because the machine continues to run when the operator steps away: 81.8 × 1.05 = 85.9 s
material: 3.1416 × 50² / 4 × 47 = 92,284 mm³ → 92.28 × 7.85 = 724 g → 0.724 × 1.90 €/kg = 1.38 €
machining operations: 85.9 / 3,600 · 40.875 = 0.98 €
Setup: 1 hour (€40.88) + Programming: 1 hour at €45 = €85.88 → Per workpiece: €85.88 / 50 = €1.72
tools, using the formula in paragraph 30.8 for each of the five tools: 0.05 + 0.11 + 0.05 + 0.05 + 0.09 = 0.35 €
overhead: 25% of (0.98 + 1.72 + 0.35) = 3.04 € → 0.76 €
Shipping and handling: €25 per order → €0.50 per workpiece
Entry€ per workpiece€ for 50 workpieces
Material (C45 bar, Ø50)1,3868,82
CNC Lathe Machining0,9848,76
Setup and Programming1,7285,88
Tools0,3517,52
Overhead expenses (25%)0,7638,04
Packaging and Shipping0,5025,00
Full cost5,68284,02
Profit (12%)0,6834,08
Calculated price6,36318,10
Offer: €6.40 per workpiece, €320.00 for 50 bushings, excluding VAT

Here, the biggest cost factor isn't the material or the cut, but the setup costs associated with programming: for a batch of 500 bushings, the cost would drop to €0.17 per workpiece. That's why the quote always specifies the quantity for which the price applies.

🖥️
Try it out in CNC Code. Write the program for the bushing in the lathe simulator: the machining time you see serves as the starting point for the estimate, without taking up time on the actual machine for testing.

30.13 Problems During Machining Operations: Causes and Solutions

When something goes wrong, the cutting edge and the chip almost always reveal why. The most common types of wear can be identified with the naked eye or with a magnifying glass:

chestsideVBside wearHigh Vc, soft gradecrateringheat on the chestrebuilt cutting edgeLow Vc, pasty materialchippingimpact, brittle
Figure 30.9 · A side view of the cutting edge, with the breast facing up and the flank on the left. The damage is shown in red: the VB wear band on the flank, the crater on the breast, the adhered material, and the chipped edge.
ProblemProbable causeRemedy
Vibrations (noise, wavy surface)Excessive tool or workpiece deflection; workpiece not clamped properly; nose radius too large; ap too small relative to the radiusShorten the overhang; use a tailstock or steady rest; use a smaller nose radius, with κr close to 90°; adjust the spindle speed by 10–20%; increase the feed rate slightly
Rapid sidewall wearVc too high; grade too soft for the material; insufficient coolingLower Vc; use a more wear-resistant grade; check the coolant flow rate and concentration
Craterization (crater on the chest)Temperature too high on the chest: Vc and high; coating not very suitableReduce Vc and then f; groove with an aluminum oxide coating; more positive geometry
Cutting edge (material bonded to the tip)Vc too low; soft material (mild steel, stainless steel, aluminum); cutting edges not sharp enoughIncrease Vc; sharp, positive cutting edge; coolant with more oil; for aluminum, uncoated polished inserts
Chips on the cutting edgeImpacts: interrupted cut, slag or sand in the stream; high feed at the inlet; material too hard and brittle; vibrationsReduce f at the entry and exit points; use a steeper angle; reinforced cutting edge (chamfer); enter in an arc or with a fillet
Groove wear along the ap lineMaterials that cause work hardening (stainless steel, superalloys) or a hard crust that always forms at the same point on the cutting edgeVary the ap between passes; smaller κr (45°) or round insert; tougher grade
Deformed cutting edge (bends downward)Temperature and pressure too high: Vc and f are excessive for the gradeReduce Vc and f; harder grade; larger nose radius
Poor finishingFeed rate too high for the nose radius; worn cutting edge; built-up edge; vibrationsReduce f or use a larger radius or a wiper insert; change the cutting edge; increase Vc; eliminate vibrations
Long, tangled chipsFeed or ap too low for the chip breaker; incorrect chip breaker geometryIncrease f; ap must be at least equal to the nose radius; chipbreaker suitable for the machining operation; high-pressure coolant
Dimensions that vary with heatingThermal expansion of the machine, workpiece, and tool during the first few hours of operation or after a shutdown; coolant that heats upMachine warm-up cycle (15–20 min) before machining; measure the workpiece at room temperature; adjust the wear compensators through frequent checks; coolant at a constant temperature
🌡️
How much does a hot workpiece expand? Steel expands by about 11.5 µm per meter per degree. A 100-mm diameter measured at a temperature 10 °C higher than the ambient temperature is 100 · 0.0000115 · 10 = 0.0115 mm, or 11.5 µm: more than half the tolerance of an H6 hole of that diameter, which is 22 µm (Chapter 14). Tight dimensions are measured when the workpiece is cold.

30.14 How to Improve a Cycle Time

Shortening the cycle time means producing more with the same machine and the same operator. Looking at Figure 30.3, it becomes clear that it’s not just about cutting speed. The main approaches are:

  • fewer passes: use a larger ap during roughing, as long as the power and insert allow (example 30.1);
  • higher feeds in finishing operations with wiper inserts, which, at the same level of roughness, operate at approximately twice the feed rate;
  • G96 in facing (Example 26.9) and cutting speeds close to the maximum production speed (Chapter 24);
  • shorter rapids: tool change points close to the workpiece, no unnecessary returns to the tool change point, tools in the turret arranged in order of use;
  • Fewer tool changes: a single tool that performs multiple operations (for example, the same insert for facing and cylindrical turning);
  • Manual operations in the background: bar loader or bar feeder, measurements taken while the machine is machining the next workpiece, in-machine probe;
  • Shorter setup times (SMED, paragraph 30.5), which are more important when batch sizes are small.
Example 30.15 · Two operations on the pivot cycle

Two changes are made to the spindle in Example 30.4 (cycle time = 201.3 s): the finishing operation switches to a wiper insert with f = 0.2 mm/rev instead of 0.1 (same speed, 1,284 rpm); the roughing passes are made 2 mm from the workpiece instead of moving away, and the rapid traverse times are reduced from 9 to 6 s.

new finishing: vf = 0.2 × 1284 = 256.8 mm/min → t = 122 / 256.8 = 0.475 min = 28.5 s (previously 57.0 s)
Roughness: with a standard insert, Ra = 0.2² × 1000 / 24.96 = 1.60 µm, at the limit; the wiper reduces it to about half that, 0.8 µm ✓
time saved: (57.0 − 28.5) + (9 − 6) = 28.5 + 3.0 = 31.5 s
new cycle: 201.3 − 31.5 = 169.8 s → reduction: 31.5 / 201.3 = 0.156
tcycle from 201.3 to 169.8 s: −15.6%, without affecting the cutting speed
first144.3 s19.0 s38.0 s201.3 safter115.8 s16.0 s38.0 s169.8 sfinishing with a wiper insert (−28.5 s) and shorter rapid returns (−3.0 s): −31.5 s, or −15.6%cuttingpassivemanual
Figure 30.10 · The cycle time of the pin before and after the two operations in Example 30.15. The manual times remain the same; a loader would be needed to reduce them.
Example 30.16 · What is the value of a 15% reduction in cycle time?

To be on the safe side, a 15% reduction in the pin’s cycle time is factored in. How much is saved per workpiece, for a batch of 200 and 2,400 workpieces per year, with a 10% markup, Ch = 40.875 €/h, and 25% overhead? And how many additional workpieces are produced per shift?

time saved per cycle: 0.15 × 201.3 = 30.2 s → with the adjustment: 30.2 × 1.10 = 33.2 s per workpiece
savings: 33.2 / 3,600 · 40.875 = 0.377 € → with overhead, 0.377 · 1.25 = 0.471 € per workpiece
batch of 200: 0.471 × 200 = 94.3 € · one year: 0.471 × 2,400 = 1,131 €
Hours of machine time saved in a year: 33.2 × 2,400 / 3,600 = 22.1 h
New time per workpiece: 201.3 × 0.85 × 1.10 + 13.5 = 171.1 × 1.10 + 13.5 = 201.7 s → 28,800 / 201.7 = 142.8 workpieces per shift (previously 122.6)
About 0.47 € per workpiece, 1,131 € and 22 machine hours per year; 20 more workpieces per shift

30.15 The Formulas in This Chapter

What Are You Looking For?FormulaUnits
Cutting timett = Σ L / vfmin
Time for the rapidstr = Lr / vrmin
Machine timetm = tt + tpmin or s
Cycle timecycle = tm + tman (manual operations only when the machine is stopped)min or s
Time per workpiecetpz = tcycle · (1 + m) + tatt / Nmin or s
OEEOEE = D · E · Qpure number
DepreciationA = (V − Vr) / na€/year
InterestsI = i · (V + Vr) / 2€/year
Hourly cost of the carCm = (A + I + S + Eel + M + Ug) / h€/h
Operator's hourly rateCo = Kaz / head€/h
Hourly cost of the workstationCh = Cm + Co / k€/h
Tool Cost per WorkpieceCu = (Ct + ts · Ch) · tt / T€
Unit Cost of a WorkpieceCpz = Cmat + (Clav + Cu + Catt / N) · (1 + sg)€
Economy LotQ* = √(2 · D · Cl / Cmag)workpieces
Break-even pointNp = (FCNC − Ftrad) / (cv,trad − cv,CNC)workpieces

30.16 Exercises

Try to solve them on your own, using a calculator, before looking at the solution.

Exercise 1. A 250-mm-long workpiece is machined flat using an 80-mm-diameter, 6-tooth end mill with Vc = 220 m/min and fz = 0.12 mm/tooth. The end mill must be fully retracted, with a 5 mm approach and a 5 mm retract. How long does the pass take?
Solution

n = 220,000 / (3.1416 × 80) = 875 rpm; vf = 0.12 × 6 × 875 = 630 mm/min; L = 250 + 80 + 10 = 340 mm; t = 340 / 630 = 0.540 min = 32.4 s.

Exercise 2. A workpiece has a cutting time of 95 s, a rapid traverse time of 8 s, and 3 tool changes of 2.5 s each. Loading and unloading, with the machine stopped, take 25 s; one workpiece out of every 10 is measured in 30 s. Find the cycle time and the number of workpieces per hour.
Solution

tcycle = 95 + 8 + 7.5 + 25 + 3 = 138.5 s; workpieces per hour = 3600 / 138.5 = 26.0.

Exercise 3. Given the cycle time from Exercise 2, a 12% safety factor, and a 1-hour setup time for a batch of 80 workpieces, what is the time per workpiece?
Solution

138.5 · 1.12 = 155.1 s; setup time for a workpiece 3600 / 80 = 45 s; tpcs = 155.1 + 45 = 200.1 s = 3.34 min.

Exercise 4. A 480-minute shift with 40 minutes of scheduled breaks; 50 minutes of downtime due to breakdowns and setup. The expected cycle time is 60 seconds; 330 workpieces were produced, 10 of which were rejected. Calculate D, E, Q, and OEE.
Solution

tpian = 440 min, tfunz = 390 min; D = 390 / 440 = 0.886; E = 330 · 1 min / 390 = 0.846; Q = 320 / 330 = 0.970; OEE = 0.886 × 0.846 × 0.970 = 0.727, approximately 73%.

Exercise 5. A machine tool costs 220,000 €, has a useful life of 10 years, and is worth 20,000 € at the end of its useful life. Interest rate: 4%; floor space: 35 m² at €90/m² per year; maintenance: 3% of the price; average power consumption: 9 kW at €0.25/kWh; tools and supplies: €3,000 per year; operating hours: 1,600 hours per year. Find the hourly cost of the machine.
Solution

A = 200,000 / 10 = 20,000 €; I = 0.04 · 120,000 = 4,800 €; S = 3,150 €; M = 6,600 €; Eel = 9 × 1,600 × 0.25 = 3,600 €; Ug = 3,000 €. Total: 41,150 €/year; Cm = 41,150 / 1,600 = 25.72 €/h.

Exercise 6. An employee has a gross annual salary of €29,000; social security contributions, severance pay, and insurance total 36%. He works 1,650 actual hours. How much does one hour of his work cost?
Solution

Kaz = 29,000 × 1.36 = 39,440 €; Co = 39,440 ÷ 1,650 = 23.90 €/h.

Exercise 7. An insert costs 10 € and has 2 cutting edges; the tool holder has dimensions of 0.30 € per cutting edge. Replacement takes 1.5 minutes, with Ch = 42 €/h. Each cutting edge lasts 12 minutes, and machining the workpiece takes 2.4 minutes with that tool. How many workpieces can be machined with one cutting edge, and what is the cost of the tool per workpiece?
Solution

Workpieces per cutting edge = 12 / 2.4 = 5. Unit price = 10 / 2 + 0.30 = 5.30 €; retainer = 1.5 / 60 · 42 = 1.05 €; Cu = (5.30 + 1.05) × 2.4 / 12 = 6.35 / 5 = 1.27 € per workpiece.

Exercise 8. On a traditional machine, a batch has a fixed cost of 15 € and a variable cost of 7.20 € per workpiece; on the CNC machine, the fixed cost is 140 € and the variable cost is 2.80 €. At what quantity does it become more cost-effective to use the CNC machine?
Solution

Np = (140 − 15) / (7.20 − 2.80) = 125 / 4.40 = 28.4: The CNC is cost-effective for 29 workpieces or more.

Exercise 9. A customer purchases 6,000 workpieces per year. Each shipment costs €80; each workpiece is worth €4, and inventory carrying costs amount to 25% of the value per year. Determine the economic order quantity and the number of shipments per year.
Solution

Cmag = 0.25 × 4 = 1 €/(workpiece · year); Q* = √(2 × 6,000 × 80 / 1) = √960,000 = 979.8, approximately 980 workpieces; runs = 6,000 / 980 = 6.1, which is practically 6 runs of 1,000 workpieces each.

Exercise 10. Batch of 500 workpieces: material cost €2.10 per workpiece; processing time per workpiece (excluding setup) 2.5 minutes at €40/hour; setup time 1.5 hours at €40/hour; tools €0.25 per workpiece; overhead: 25% of machining operations costs. How much does each workpiece cost?
Solution

Machining 2.5 / 60 · 40 = 1.667 €; setup 60 / 500 = 0.12 €; total machining operations costs 1.667 + 0.12 + 0.25 = 2.037 €; overhead 0.509 €; Cpz = 2.10 + 2.037 + 0.509 = 4.65 €.

Exercise 11. A workpiece is produced in quantities of 10,000 per year. If the time per workpiece is reduced from 180 to 150 seconds, how many machine hours are freed up, and how much is saved, given that Ch = 45 €/h?
Solution

30 s · 10,000 = 300,000 s = 83.3 h; savings of 83.3 · 45 = 3,750 € per year.

Exercise 12. When turning a long, thin shaft made of mild steel at Vc = 60 m/min, the surface comes out dull and rough; material is visible stuck to the tip of the insert, and a whistling sound can be heard. What is happening, and how should you respond?
Solution

There are two problems. The glued material is causing a built-up edge, due to a cutting speed that is too low for mild steel: increase Vc to the values in the table (180–250 m/min with carbide) and use a sharp, positive-rake cutting edge. The whistling sound indicates vibration, because the shaft is long and thin: support it with the tailstock or a steady rest, use a small nose radius, and set κr close to 90°.